That Cabinet:
1. Approved the adoption of the flexible, blended redevelopment approach set out in the Southwold Caravan Site Forward Strategy reported to the Southwold Harbour Management Committee in March 2025 involving a combination of static caravans, lodges and touring pitches.
2. Approved progression to a ten-year rolling licence model for static caravan plots, to replace the informal seasonal licences currently in place, subject to legal review and advice.
3. Endorsed the phased procurement strategy covering design consultancy, site infrastructure works, and the sourcing of caravan and lodge units via market engagement and competitive procedures.
4. Authorised the immediate procurement of a Design Manager through a compliant framework call-off process, within current delegated financial authority.
5. Noted the continuing stakeholder engagement programme with static pitch holders and local consultees, alongside the application of a structured plot allocation framework.
6. Approved continued development and implementation of the Phase 1 mobilisation programme, with a targeted delivery window from December 2026 to April 2027.
7. Approved up to £250,000 for design management costs, set out in paragraph 4.3 to be funded by harbour reserves.