6
The Committee received report ES/2327. The application sought retrospective Planning Permission for the erection of a large building, surrounded by hardstanding, and associated works, for a plant hire company, located towards the western side of the Sinks Pit/Kesgrave Quarry Site. The area of proposed building and the existing operations within the former minerals extraction site were located within the parish of Little Bealings although the site entrance falls within Kesgrave.
The application was called in for determination by Planning Committee by the Head of Planning and Building Control, on the basis of the significance in terms of scale, effects and public interest. A site visit by Members of the Planning Committee took place prior to this application being considered and the notes were on the website.
The Principal Planner ran through maps of the site, pointing out key features and the Public Right of Way. She gave a brief overview of the extensive planning history of the site. Planning permission was previously granted on the same area of land for two buildings, hardstanding and associated works, for the same purpose (DC/19/2666/FUL). However, the developer did not discharge the pre-commencement conditions on that planning permission before starting works on site, and the works they have undertaken do not accord with the approved plans. Therefore, that consent had now lapsed.
The Principal Planner showed photographs of the site highlighting the key elements of the site including the bund, HQ building, mineral and aggregates processing area, concrete plant, weigh station and the application site.
The Principal Planner shared plans of the building, highlighting the different areas and ran through the material planning considerations and key issues. The site was supported by paragraph 125 of the NPPF and SCLP 2.1. She pointed out the nearest residential properties to the application site. The bund and low-lying site meant there weren’t the usual concerns about shadowing and loss of privacy. The main concerns raised by third parties related to noise and vibration, working hours and light pollution, some of which related to existing operations on the site. There were ongoing issues but the existing authorised operations were the ones that created the noise. The Principal Planner pointed out that Members had to consider this application alone and not about controlling existing activities and uses elsewhere on the site. She pointed out that the conditions detailed in the report would control the hours of work, which would be the same as the HQ building. There were also conditions relating to ventilation and there would be an alert system for the workshop doors relating to noise levels. If a preset noise level was breached it would alert those on site to close the doors. Lighting had been designed for ecological considerations and residential amenity and there were conditions relating to this. It was therefore considered that the scheme was acceptable in terms of residential amenity.
Third party comments raised concerns about Highway safety but there had been no objections or concerns raised by the Highways Authority. The scheme was acceptable in terms of surface water runoff, drainage, contamination and impacts upon the SSSI. She explained they were awaiting a drainage consultation report, which was a technical matter that could have been a condition, but the Applicant has chosen to clear it before final paperwork was issued. Issues were identified regarding ground gases travelling below ground from the landfill site but investigations have been undertaken to ensure use of the application building and the HQ were not at risk of a build-up of gases. The Principal Planner explained there were elements of sustainable construction and holistic water management including solar panels and greywater reuse.
The Principal Planner finished by stating that the recommendation was to approve subject to conditions with the addition of the change shown in the update sheet, which would enable officers to resolve the technical issues relating to the drainage verification report.
Councillor McCallum asked about the opening times on p37 paragraph 3.4. The Principal Planner explained it had been included in the update sheet that Sunday was an error and should have been Saturday.
Councillor Ninnmey asked about the increase in vehicles and was there any detail about the number of vehicles, times and if it would be a continuous flow of traffic. The Principal Planner explained it was an operational site and they would expect peaks at the start and end of the day. The Chair suggested that the applicant may be able to answer this question.
Councillor Hedgley asked for clarity that there were two applications before this which lapsed and so this was a new building that had no planning permission and therefore it was retrospective. The Principal Planner confirmed this. Councillor Hedgley asked for the site photo to be reshown and pointed out that the building was surrounded by many items of plant and it wasn’t an isolated building.
Councillor Deacon asked about the alarm system and if the doors closed automatically. The Principal Planner explained a light would show in the building and a message sent to the managers telling them to shut the doors. These incidents would be automatically recorded and East Suffolk would be able to access these records if there were reports of excessive noise to check compliance.
Councillor Byatt asked if there were records of complaints from residents about this site. The Principal Planner explained there were numerous complaints about the wider site, however action couldn’t be taken until they isolated where the noise came from and the noise came from areas that already had consent. She pointed out that they were seeking to control noise on this application through conditions.
Councillor Daly asked if any enforcement was undertaken when the building was constructed. The Principal Planner confirmed that the application was submitted as a result of enforcement action.
Councillor Hedgley commented that the complaints must be pushing a thousand.
The Chair invited Mr Thornborrow, a resident and representative of the Sinks Valley Environmental Protection Group, to make his representation. He said there had been well over 5,000 complaints against the Tru group about noise on the site and that residents of Little Bealings were long suffering and some had medical conditions as a result. He agreed that much had been done to mitigate noise nuisance and there was an agreed plan with the Environment Agency. He accepted that the building would help mitigate the noise, as work that used to be undertaken outside would now take place inside. However, it remained to be seen if noisy activity outside still remained and it would only benefit residents if it accords with the noise management plan. He requested that suitable conditions were included and technology, systems and processes were in place to ensure adherence to the management plan.
Councillor Deacon asked if he would be satisfied with the noise control measures mentioned already. Mr Thornborrow did not know if the noise mitigation measures would work or not.
Councillor Hedgley asked Mr Thornborrow to elaborate about the medical issues residents were experiencing. Mr Thornborrow explained that the stress caused to residents from the noise had resulted in them requiring medication to alleviate the stress.
Councillor Ninnmey asked about the bund. Mr Thornborrow said the bund was there before the Tru Group era and it was there to mitigate the noise from the previous occupants. However the bund had eroded over time and although they had continually asked for the agencies, namely Suffolk County Council, to raise the height of the bund this had been declined.
Councillor Byatt asked about the opening hours and working on Saturdays. Mr Thornborrow said the site was already operational on Saturday mornings but would not like the hours to be increased. He didn’t think a Sunday would be likely as generally the construction industry did not work on Sundays.
Ian Ransome from Little Bealings Parish Council was invited to make his representation. He stated that the Parish Council objected to the application on the grounds of concerns about surface water drainage, noise and development in the countryside. He pointed out that the Parish Council didn’t object to the previous application which was closer to the bund. The Parish Council was concerned that the concrete yard around the building would continue to cause noise as would other activities. He explained that the site had a Hollywood bowl effect on local residents with noise coming up over the bund. As all the activities on site generated noise the Council felt there should be a maximum dBA noise level not an average level and that you can not consider this application site in isolation. He also asked why Members didn’t visit places outside of the site to get an idea of the noise levels.
Councillor Deacon asked his views on noise mitigation measures. Mr Ransome hoped that the measures would mitigate the noise and that the doors would be shut when the noise was excessive. He was still concerned about noisy outside activities, such as the use of jackhammers.
Councillor Hedgley asked for clarity on max and average dBA levels. Mr Ransome explained the dBA was a graph/scale showing normal human hearing range. He said most testing by East Suffolk, Suffolk County Council and the Environment Agency looked at an average noise level which meant any sudden high peaks were levelled out. The Parish Council would like a maximum sound level imposed.
Councillor Hedgley asked how many complaints had been submitted. Mr Ransome believed there were 5.5k complaints.
Councillor Ninnmey asked about the degree of erosion of the bund and what needed to be done to make it effective again. Mr Ransome said the bund had eroded. He was aware that the Tru company did apply for an acoustic fence on top of the bund but that planning application had expired. He said they were also going to increase the bund but that didn’t protect properties higher up on Playford Road. He mentioned that when he was at Pine Hills, near the western side of the site, you could still hear the noise from the site even though they had triple glazing.
Councillor Byatt asked what results had come about because of the complaints and if any action had been taken. Mr Ransome said the company had undertaken work with its noise consultants and some of it had been successful. A noise abatement had been issued by East Suffolk. He said the sporadic and intense noise was very disturbing for residents.
Councillor Bennett noted that air pollution levels were also a similar concept of averages. He took on board the comment about the site visit and agreed that they should have visited the wider area. He asked what time period the complaints covered. Mr Ransome said Tru Group operated from 2014 but up until 2019/20 the Parish Council couldn’t get all the agencies involved. The community liaison group had achieved a considerable amount and a lot of noise had been contained. They had concerns about the mineral area of the site and the plant storage and associated activities caused noise. He noted that not all days were the same with it being quiet today but Friday afternoon was horrendous.
Councillor McCallum asked about the washing of the concrete mixer drums and if the noise issue had been resolved. Mr Ransome confirmed that it was not as bad as it had been.
Alec Bird and Laura Thomas were invited to make their representation on behalf of the Applicant. Alec thanked Members for considering the application and was pleased the recommendation was to approve. He explained the business was part of the community and they contributed to it, not just because they were a large employer for the local area. Laura asked Members to guard against speculation over noise issues as these were linked but not determinative. She explained the Biodiversity enhancement strategy for the site was very positive and the company was keen to establish community engagement.
Councillor Daly asked about the planning history and why they were given planning permission twice but then erected a building without permission. Alec explained that the company grew very quickly but it was now being run differently. The building had been in process since 2019 and the owner thought he was acting in the spirit of the consent that was granted but that it was just a variation. The build had continued because of the time taken to reach this position of getting planning permission.
Councillor Deacon expressed his disappointed that this was a retrospective application. He also asked for an explanation about the noise mitigation. Alec apologised for the situation. He explained that when a noise complaint was made, if 10-20 residents made complaints about the event to all three agencies each one counted as an individual complaint, meaning the number of complaints looked higher than they really were. The company was actively seeking least noisy machinery, building walls to shield the noise, modifying machinery, implementing good HR practices and culture changes, training and policing the operating hours. They were trying to shroud vehicles and using white noise reversing bleepers on vehicles to reduce the noise. They were also looking at a digital AI system to remove bleepers completely. He explained that they operated in compliance with their licence and that the contention came from the legacy of what the company had inherited.
Councillor Deacon explained he was asking about noise mitigation measures for the application building. Alec explained that staff would be pre-emptive and shut doors before noisy activity took place and that the detectors were a backup if activity exceeded the noise threshold and then the doors would be shut. Councillor Deacon felt that the action would be retrospective like the planning application. Alec confirmed that they intended to shut the doors first.
Councillor Hedgley felt it was a good tour last Thursday and that it was a professional organisation that was part of the community. He asked how much had been given to the communities of Kesgrave and Little Bealings. Councillor McCallum felt this was irrelevant and not a planning matter. The Chair allowed it but said they could choose not to answer. Alec explained he would not give explicit facts and figures but that the company wanted to be part of the community. It was owned and led by a family who had lived in East Suffolk for three generations and they employed 150 people from the local area. He said they supported the community and Laura said they had already reached out to the local primary school about taking plant to the school for an educational visit.
The Head of Planning and Building Control pointed out that investment into a community was not a planning matter and it should not influence the decision by the Members.
Councillor McCallum stated that she did not want to see an application determined on how much a community did and didn’t get and that the decision should be based on planning matters. The Chair explained he allowed the question for contextual reasons.
Councillor Ninnmey expressed surprised that the application was retrospective. He asked how many of the complaints were since they took over the site and why they were not using noise level measuring to automatically close the doors. He noted that the bund had eroded and there was reference to an acoustic barrier. He asked if there were any intentions to improve the bund. Alec noted the dissatisfaction regarding the retrospective nature of the application. He explained that the last consent was given in 2019 and the process from then to here in 2025 had included ongoing engagement with the planners. He said it was a very complicated site under modern rules and there was never any intention to side step the process. With regards to the bund the area in their ownership was generally high and they had been able to maintain it as it didn’t back onto the landfill site. Where the bund was lower, outside of the application site, they had looked at a noise barrier. However the increase in weight and pressure on the bund would put pressure on the landfill site and Suffolk County Council has raised concerns. They have been unable to find a consultant who would sign off building up the bund and putting in a fence. Because the bund was full of waste on the eastern side it was not technically and financially viable to increase the height or put in the acoustic barrier. He explained that the dB levels were regulated by Suffolk County Council, East Suffolk and the Environment Agency and their last three audits from the Environment Agency were clean and were facing no enforcement action from County. They were working with one resident and the liaison group to resolve a vibration issue at one property. He stated that they were compliant with BS 4142 in relation to noise emissions. Laura explained that auto closing doors were a hazard that could cause more issues than they solved so this proposal was considered the safest for those working on the site.
Councillor Ninnmey felt the position of the building worsened the impact on the residents as it was further from the bund and nothing could be done to improve the bund or add an acoustic barrier. He was concerned that the problems for the community wouldn’t be mitigated. He asked why they moved the location of the building. Alec felt that was not a fair assessment. He explained that the location was chosen to support the flow of traffic and ensure safety of the operatives. The siting would minimise the movement of heavy traffic and therefore reduce the noise.
Councillor Reeves asked about Health and Safety. Laura explained that closed doors raised questions about ventilation but there would be risk assessments for use of PPE. The way the building was designed reduced vehicle movements, especially reversing movements, and so reduced the interface between vehicles and pedestrians. She pointed out that there would be continuous reviews and assessments.
Councillor Reeves asked about air conditioning. Alec explained there was underfloor heating in the workshop powered by an air source heat pump and also air con. There was an extraction system when the doors were closed. However because access and egress was constant air con wasn’t entirely practical but the system would have a cooling effect and workers would be given breaks.
Councillor McCallum asked if it was correct that two thirds of their power requirements would be produced onsite through solar panels. Alec confirmed it was correct and stated that unfortunately battery storage was not possible.
Councillor Byatt asked about bat boxes and other ecological offerings and if they were the right things. Laura explained they had a biodiversity strategy plan which included thinning and coppicing of woodland together with bird and bat boxes.
Councillor Bennett asked about the community liaison group and if the application could have been discussed more robustly by the group. Alec said it had been discussed and they attended the quarterly meetings. He felt that sometimes the meetings were not very productive as there was a lot of technical information being presented to people who were not technical. He acknowledged that the site was contentious but stressed that a lot of the issues were inherited. However they had made progress in forming a better dialogue between residents and the company so they could now communicate independently of the liaison group and the site was less contentious now than it used to be.
Councillor Byatt asked about wet areas and if the ecological work would extend to those areas. Alec said they were doing positive things within the boundary of the land they owned. The ponds from the old quarry were sown as wild meadow and they have maintained beehives. They purchased land to the east of the drive two years ago and have an emerging ambition to provide forest schooling in that area.
The Head of Planning and Building Control reminded members that they needed to consider this site and not the issues across the wider site. He explained that the Community Liaison group had attendance from East Suffolk’s Strategic Director, County and District Councillors and the Principal Planner and it was useful for resolving issues.
Councillor McCallum acknowledged that no-one liked retrospective applications, but they had to look at the application no differently from any other application. She noted that the footprint was smaller than the previous application. Lots of consideration had gone into how the building was built and the health and safety. Noise complaints would be dealt with by the Environmental Protection team and issues have been and still are dealt with. She had stood in a resident’s garden and heard the noise so was aware of the issues. She hoped that residents would report any noise so conditions were adhered to. Kesgrave Town Council supported the application and so did she. She pointed out that the road was kept clean and immaculate, the company was a strong employer and this was sustainable. Kesgrave benefitted from this business and Little Bealings could also benefit. She would be proposing approval.
Councillor Daly noted there had been a big, wide discussion. In terms of noise it would be an improvement and he was encouraged by the ecology side so on balance he would support this application.
Councillor Hedgley explained the membership of the Liaison group. There was a worry about retrospective applications and if the Westerfield Quarry went ahead traffic and noise would increase. He asked that the condition about noise was changed so that the noise mitigation plan was statutory.
Councillor Byatt concurred and asked if there could be random checks on noise and pollution. He mentioned the northern relief road and how that would impact residents so it was important to monitor noise. He noted it was a strong local company and was pleased about the solar panels so he would support the application.
Councillor Deacon stated that he didn’t like retrospective applications but would support as long as the door monitoring system was beefed up.
Councillors Reeves wanted to see something in the conditions that addressed the employees in the space and protected them against noise. He also stated that he was against retrospective planning applications.
The Planning Principal explained that employee safety would be covered by H&S legislation so they shouldn’t duplicate in conditions. The Head of Planning and Building Control would seek reassurance from the Applicant but was sure they didn’t want the safety of employees to be compromised.
The Principal Planner explained that the noise management plan covered the whole site but these conditions were only related to the application site. The issue was trying to identify which consent has been breached. She explained that they could only put in conditions that could be enforced.
Councillor Hedgley wanted condition 9 beefed up with a noise management plan for this building and wanted monitoring outside the building. The Head of Planning and Building Control explained that there should be a proactive enforcement approach and although they couldn’t monitor all the time they would have access to data.
The Chair stated that if the company breached the conditions they would suffer and future applications would note this.
Councillor Ninnmey suggested a monitor on each site to have a means of determining location of noise. He also felt that it had not been clear if the complaints were recent or if the number of complaints had fallen in recent years. The Head of Planning and Building Control said it was not practical to refine dB measuring and Councillor McCallum felt residents needed to inform the council if there were noise issues.
On the proposal of Councillor McCallum, seconded by Councillor Daly it was
RESOLVED
That the application be approved subject to the consideration of comments from statutory consultees in relation to the technical details of the drainage verification report (and/or additional/revised drainage details), and
1.1. Subject to the statutory consultees being satisfied with the technical details within the recently submitted drainage verification report, this scheme should be approved subject to appropriate conditions.
1.2. Whilst many of the conditions will need to have similarities those conditions included on the previous consent for two buildings, as this scheme is retrospective, they will need to be worded differently and require the implementation and retention of a number of details that have been submitted as part of this application rather than the submission of details prior to implementation (i.e. those elements that were previously the subject of pre-commencement conditions).
1.3. There is no need to include the usual standard time limit for implementation as the building has already been constructed, so the consent will have been implemented prior to the decision notice being issued.
1.4. There is no need for a Biodiversity Net Gain (BNG) condition because the application was submitted prior to the introduction of BNG and therefore exempt from those requirements.
1.5. Therefore the recommendation is one of authority to approve subject to the statutory consultees being satisfied with the technical details of the drainage verification report, and subject to the conditions relating to be matters outlined below.
Conditions
1) Approved documents and drawings
2) Use limited to that proposed
3) Machinery and vehicle repairs within building only
4) Vehicle washing in designated areas
5) Operational hours
6) Hours of use of ventilation and similar equipment
7) Ventilation equipment approved/to be installed
8) Any further ventilation equipment will require approval
9) Workspace noise/doors monitoring system
10) Vehicular movements within the site
11) Parking/turning areas
12) Electric vehicle charging points and cycle storage/parking
13) Strategy for the disposal of surface water
14) Drainage verification report /implementation of final elements of drainage
15) External lighting scheme
16) No further external lighting on site or on building without prior approval
17) Implementation of the biodiversity enhancement strategy
18) Unexpected contamination
Informatives
1) Highlighting which conditions are to be complied with prior to first use
2) Reasons for approval
3) Conditions and requirements of other planning consents still apply
4) Future on site works are likely to require planning permission:
5) Building regulations and impacts upon this planning permission:
6) Other legislation and consents/permits:
7) Contamination, Ground Gas and developer/landowner responsibility
8) Proximity to site of special scientific interest (SSSI)
9) Protected trees along access
10) Works in highway
11) Public rights of way:
12) Surface water and water courses
13) Future advertisements and signage
14) Naming/numbering of new buildings
15) Sprinkler systems
16) Biodiversity net gain exempt