Decision Details

  • General
  • Reports

This section allows you to view the general details of a Decision

Details

Status:
Implemented
Business Item
Sea Link Nationally Strategic Infrastructure Project – Statutory Consultation Response
Ref.
ES/1795
Is a Key Decision:
No
Decision Type:
Committee
Decision Maker:
Cabinet
Date of Decision
Tue 2 Jan 2024
Show on Forward Plan
No
Description
Report of the Cabinet Member with responsibility for Energy and Climate Change.
Matter for Decision (to consider...)
To provide a response to the statutory consultation on the Sea Link Nationally Significant Infrastructure Project and to delegate authority to the Head of Planning and Coastal Management to undertake all further activities in relation to the Sea Link project during the pre-application, examination and post examination/consent phases including the signing of any legal agreements/memorandum of understandings
Service Area
Planning & Coastal Management
Service Area 2
Not Applicable
Contact for Background Papers:

Philip Ridley

Head of Planning and Coastal Management

philip.ridley@eastsuffolk.gov.uk

Background Papers:
See attached report.
Is Decision District Wide
No
Decision Made

1. That the consultation response as set out in Appendix A to report ES/1795 be agreed.

 

2. That authority be delegated to the Head of Planning & Coastal Management, in Consultation with the relevant Cabinet Member(s), to act on behalf of the Council in all activities associated with the pre-application, examination and post examination/consent phases of the project including the signing of any legal agreements/memorandum of understandings.

Reason for Decision

1. As the project progresses through the consenting process, it is appropriate for the Council to engage with the applicant to ensure that in the event the scheme is consented by the Secretary of State, the impacts of the project are appropriate mitigated and if appropriate compensation provided in addition to ensuring the community is appropriately compensated.

 

2. There will be a future time for comments in the form of Relevant Representations on the proposal when it is submitted to the Planning Inspectorate for examination. In addition to this during the examination there will be multiple unrelenting deadlines to meet and if consented, requirements to discharge during the post consent phase. By virtue of the number and frequency of deadlines it is not possible to present reports to Cabinet seeking agreement on each occasion. Delegated authority was therefore sought to allow the Head of Planning & Coastal Management to respond and fully engage in the pre-application, examination, and post consent phases of the process, including the signing of any legal agreements/memorandums of understandings in consultation with the relevant portfolio holder on behalf of Cabinet.

Alternative Options Considered and Rejected
To not agree the consultation response and to not agree to provide the requested delegated authority. 
Any Declarations of Interest Declared
Councillor Whitelock declared a Non-Registerable Interest as the item related to her ward.
Any Dispensation Granted
None.

Decision Criteria

This Decision does not contain any decision criteria records.

Wards

Aldeburgh and Leiston; Kelsale and Yoxford; Saxmundham

Topics

This Decision does not contain any Topic records

Overview and Scrutiny

This Decision does not contain any Overview and Scrutiny records.

This section allows you to view the reports for the Decision.

This section displays the history of the Decision.

Decision History

Date & Time CreatedUser Full NameStatus DescriptionDetails
123
 Page 1 of 3, items 1 to 10 of 22.
18/12/2023 16:51:56Matt MakinBusiness Item Created 
18/12/2023 16:51:56Matt MakinCommittee AddedCabinet
18/12/2023 16:51:56Matt MakinMeeting Added02/01/2024 6:30PM
18/12/2023 16:53:07Matt MakinWard AddedAldeburgh and Leiston
18/12/2023 16:53:07Matt MakinWard AddedKelsale and Yoxford
18/12/2023 16:53:07Matt MakinWard AddedSaxmundham
18/12/2023 16:53:16 General Details EditedReference Number Generated (ES/1795)
18/12/2023 16:53:16Matt MakinStatus ChangedDecision Scheduled [1]
18/12/2023 16:57:37Matt MakinReport AddedDocument ID 25208: ES-1795 Appendix A
18/12/2023 16:57:41Matt MakinReport AddedDocument ID 25209: ES-1795 Sea Link NSIP - Statutory Consultation Response

Approval/Comments